    Automated planning of concrete joint layouts with 4D-BIM

    مقاله: Automated planning of concrete joint layouts with 4D-BIM


     
    Authors: Moslem Sheikhkhoshkara, Farzad Pour Rahimiana,⁎, Mohammad Hossein Kavehb
    M. Reza Hosseinic, David J. Edwardsd
     
    Publish : Automation in Construction , 2019
     
    Abstract
    This study reports on developing an innovative approach for the parametric analysis of daylighting and visual comfort, through a sun Concrete pouring represents a major critical path activity that is often affected by design limitations, structural
    considerations and on-site operational constraints. As such, meticulous planning is required to ensure that both
    the aesthetic and structural integrity of joints between cast in-situ components is achieved. Failure to adequately
    plan concrete pouring could lead to structural defects, construction rework or structural instability, all having
    major financial implications. Given the inherent complexity of large-scale construction projects, the ‘manual
    planning’ of concrete pouring is a challenging task and prone to human errors. Against this backdrop, this study
    developed 4D Building Information Management (BIM) approach to facilitate automated concrete joint positioning
    solution (as a proof of concept) for design professionals and contractors. The study first developed
    structural model in Revit, then extracted spatial information regarding all construction joints and linked them to
    dynamic Microsoft (MS) Excel and Matlab spreadsheets using integration facilitated by Dynamo software.
    Midspan points of each beam as well as floor perimeter information were gathered via codes developed in MS
    Excel macros. Based on the Excel outputs, Matlab programming was used to determine best concreating starting
    points and directions, and daily allowed concrete volume, considering limitations due to cold joints. These
    information were then pushed back to Revit via Dynamo in order to develop daily concrete scheduling. The
    developed automated programme framework offers a cost-effective and accurate methodology to address the
    limitations and inefficiencies of traditional methods of designing construction joints and planning pours. This
    framework extends the body of knowledge by introducing innovative solutions to integrate structural design
    considerations, constructional procedures and operational aspects for mitigating human error, and providing a
    novel, yet technically sound, basis for further application of BIM in structural engineering
     
    برای دانلود این مقاله وارد حساب کاربری خود شوید.
     
    بعد از ورود لینک دانلود قابل نمایش میگردد
     

    نظرات (0)

    هیچ نظری در اینجا وجود ندارد

    نظر خود را اضافه کنید.

    1. ارسال نظر بعنوان یک مهمان ثبت نام یا ورود به حساب کاربری خود.
    پیوست ها (0 / 3)
    مکان خود را به اشتراک بگذارید
    © 2015 Your Company. All Rights Reserved. Designed By JoomShaper

    Search